This is what we were waiting for: a giant crane. The crane got moved back a bunch of times by the city. So it put our schedule behind. But we’re still racing to get open for Saturday, Clover’s 3rd anniversary from the date we sold our first sandwich at MIT.
The crane came yesterday. It was enormous. 80 Ton crane. They had to shut down Cambridge St. Within 3 hours of the HVAC units getting placed on the roof there was heat in the space. Seriously. It was that fast. Really impossibly fast. It’s very exciting.
Our health inspection is complete. We have a few more inspections tomorrow morning. If everything goes well we’ll be ready to serve you all on Saturday. Can’t wait!